The main structure of the group's people's livelihood project "capped", and the company moved to a new level
- Categories:Group News
- Author:
- Origin:
- Time of issue:2020-07-21
- Views:0
(Summary description)On the morning of July 20th, the complex building of the Xiangdong District Traditional Chinese Medicine Hospital project site was hung up on the "Xifeng Golden Roof". We braved the sweltering heat to forge ahead, overcome the difficulties brought by the epidemic period, and solve the various problems. From a flat land to a perfect ceiling, every corner is condensed with the hard work and sweat of the workers. The quality of products and the speed of construction go hand in hand. It is not only the contribution of the builders who fight day and night on the construction site, but also the profound interpretation of the spirit of Chengtou.
The main structure of the group's people's livelihood project "capped", and the company moved to a new level
(Summary description)On the morning of July 20th, the complex building of the Xiangdong District Traditional Chinese Medicine Hospital project site was hung up on the "Xifeng Golden Roof". We braved the sweltering heat to forge ahead, overcome the difficulties brought by the epidemic period, and solve the various problems. From a flat land to a perfect ceiling, every corner is condensed with the hard work and sweat of the workers. The quality of products and the speed of construction go hand in hand. It is not only the contribution of the builders who fight day and night on the construction site, but also the profound interpretation of the spirit of Chengtou.
- Categories:Group News
- Author:
- Origin:
- Time of issue:2020-07-21
- Views:0
On the morning of July 20th, the complex building of the Xiangdong District Traditional Chinese Medicine Hospital project site was hung up on the "Xifeng Golden Roof". We braved the sweltering heat to forge ahead, overcome the difficulties brought by the epidemic period, and solve the various problems. From a flat land to a perfect ceiling, every corner is condensed with the hard work and sweat of the workers. The quality of products and the speed of construction go hand in hand. It is not only the contribution of the builders who fight day and night on the construction site, but also the profound interpretation of the spirit of Chengtou.
Up to now, the overall completion of the overall relocation and reconstruction project of the Chinese Medicine Hospital is as follows:
①The basement and main body (including the frame layer) of the complex building were completed on July 19, and the roof was capped 42 days earlier than the original plan on August 31. The wall masonry is currently in progress;
②The main body and foundation of the infection building, the mental hospital building, and the sewage treatment room have been completed, and the main experience and roof waterproofing have been completed. The window frames, external wall insulation and real stone paint have been completed, and the decoration model rooms of the infection building have been basically completed;
③The main body of the rehabilitation building (including the frame layer) has been completed, and the wall masonry has been basically completed. At present, the interior and exterior walls are mainly painted;
④The basement clinic has completed the basement and the main body (including the frame layer), the wall masonry has been basically completed, the foundation pit backfilling has been completed, and the external wall dry hanging stone construction is in progress;
⑤The basement garage has been completed, and the foundation pit backfill has been basically completed.
The successful topping of the main structure of the project is a result of the care and support of the leaders of the Municipal Urban Investment Group and the District Committee and District Government, as well as the joint efforts of the project construction, construction, and supervision units, grabbing progress nodes, and ensuring quality and quantity. It is not only It represents the completion of a stage of work, and at the same time turned a new page in the progress of the project. Next, the main project will enter the construction stage of secondary structure, installation and decoration. We always adhere to high standards and strict requirements, and use advanced technology. Technology and standardized operations strictly require every aspect of the construction, extreme consideration, step by step precision work, product quality and construction speed go hand in hand, high-quality, fast and safe completion of the construction of the Chinese Medicine Hospital project.
Scan the QR code to read on your phone
Recommended News
Yu Xiuming, secretary of the Yichun Municipal Party Committee, went to the construction site of the sports park to investigate
Huang Dongsheng, Secretary of the Disciplinary Committee of Yichun City, inspected the projects undertaken by our group
CONTACT US
Address: Taifeng holding building, Jiulong Avenue, Nanchang, Jiangxi
Tel:86-791-83972766
E-mail:jxtfjs@163.com
Post code:330000
Copyright © 2021 TaiFeng Holding 赣ICP备2021005078号-1 Powered by www.300.cn
WeChat official account